Late on 1 June 2012, Tokyo Electric Power Company officials announced that more than half the thermometers on Fukushima Daiichi Reactor 2 have failed, or are failing!
TEPCo says 23 of the 41 thermometers are not working. The thermometers are critical to maintaining safe temps inside the disable GE designed reactor.
Back in February 2012, failing temp gauges on Reactor 2 caused temps to rise above official cold shut down standards. TEPCo later claimed it was simply a faulty gauge.
By March 2012, TEPCo actually stopped taking readings off several gauges on Reactor 1 as well as Reactor 2.
TEPCo says they will try to install new gauges…in July!!!